Construction Updates

  • Through access to the alley will be closed week of 4/24. 
  • Eastbound curb lane closure to continue on South Charles St.
  • Week of 4/24 will be the final week trucks enter the project site through the alley.  
Construction Update 4.21.2023 Cover Image

Construction Update 4.21.2023

Through access to the alley will be closed week of 4/24. Click the link below to see the full update.

  • Trucks and heavy equipment will continue entering and exiting the project site through the alley. 
  • S Charles St East bound curb lane will be closed the week of March 20th. Uniformed police officer and traffic control supervisor will be present to direct traffic. 
  • Temporary no parking will be in place to provide clearance for trucks on Hiawatha and S Bush Pl. 
  • Alley will be shut down to through traffic the week of April 3rd with continued access to 999 Hiawatha parking garage.
Construction Update 3.20.2023 Cover Image

Construction Update 3.20.2023

Trucks and heavy equipment will continue entering and exiting the project site through the alley. Click the link below to see the full update.

  • Rainier Ave and S Charles St curb lane closure times to shift to 9am - 5pm. 
  • Concrete trucks to enter and exit the site through the alley Monday, February 20th. 
  • Trucks to enter and exit the alley the week of February 20th exporting soil. A section of the South curb on S Bush St is a no parking zone. 
Construction Update 2.17.22 Cover Image

Construction Update 2.17.22

Rainier Ave and S Charles St curb lane closure times to shift to 9am - 5pm. Click the link below to see the full update.

  • Trucks will continue entering and exiting the project through the alley the week of March 13th. 
  • The Eastbound curb lane on S Charles St will be closed to pedestrian traffic. 
Construction Update 3.13.2023 Cover Image

Construction Update 3.13.2023

Trucks will continue entering and exiting the alley the week of March 13th. Click the link below to see the full update.

  • Seattle City Light will provide temporary power to 1130 Rainier Ave S and 900 Rainier job site on Saturday, February 11th. Expect traffic in alley. 
  • 24/7 closure of Northbound curb lane on Rainier Ave S to continue the week of February 13th. Uniformed police officer will be present from 6-9am and 3-6pm. 
  • Trucks and equipment to continue entering and exiting the job site the week of February 13th. 
Construction Update 2.10.23 Cover Image

Construction Update 2.10.23

Seattle City Light will provide temporary power to 1130 Rainier Ave S and 900 Rainier job site on Saturday, February 11th. Click the link below to see the full update.

  • Rainier Avenue's right northbound lane will be closed from February 6th through February 18th with uniformed police officer directing traffic from 6-9am and 3-6pm. 
  • Trucks to continue entering and exiting the job site on S Charles St and the alley the week of February 6th. 
Construction Update 2.6.23 Cover Image

Construction Update 2.6.23

Rainier Avenue's right northbound lane will be closed from February 6th through February 18th with uniformed police officer directing traffic from 6-9am and 3-6pm. Click the link below to see the full update.

  • Rainier Ave and S Charles St sidewalks to remain closed the week of January 30th. 
  • S Charles St eastbound lane to remain closed the week of January 30th from 9am to 5pm. Uniformed police officer will be present. 
  • Trucks to continue entering and exiting the job site the week of January 30th. 
  • Alley closure will occur Wednesday, February 1st and Thursday, February 2nd with continued access to 999 Hiawatha parking garage. 
Construction Update 1.27.23 Cover Image

Construction Update 1.27.23

Rainier Ave and S Charles St sidewalks to remain closed the week of January 30th. Click the link below to see the full update.

  • Drilling equipment to mobilize on site Monday, January 23rd. Equipment to enter the site from S Charles St. 
  • Curb lane closure on Rainier Ave S and S Charles St  to occur the week of January 23rd from 9am to 5pm. Expect uniformed police officer, signage and traffic control devices to aid directing traffic. 
  • Sidewalk closure to occur on Rainier Ave and S Charles St the week of January 23rd from 7am to 5pm. 
  • Trucks to enter and exit the site through the alley the week of January 23rd. 
Construction Update 1.22.23 Cover Image

Construction Update 1.22.23

Drilling equipment to mobilize on site Monday, January 23rd. Equipment to enter the site from S Charles St. Click the link below to see the full update.

  • Excavation to continue the week of January 16th. Trucks and equipment to enter and exit the site on S Charles St and alley.
  • Concrete trucks to enter and exit the site Friday, January 20th. 
Construction Update 1.13.22 Cover Image

Construction Update 1.13.22

Excavation work to continue the week of January 16th. Trucks and equipment to enter and exit the site on S Charles St and alley.

  • Potholing and trucking in alley the week of January 9th. Expect alley closure with continued access to 999 Hiawatha parking garage. 
  • Demolition of concrete slab under former 900 Rainier building the week of January 9th. Trucks and equipment to enter and exit the site from S Charles St. 
Construction Update 1.6.2023 Cover Image

Construction Update 1.6.2023

Potholing and trucking in alley the week of January 9th. Expect alley closure with continued access to 999 Hiawatha parking garage. Click the link below to see the full update.

  • Equipment to mobilize for trenching the week of December 19th. Alley will be closed on Monday, December 19th with continued access to 999 Hiawatha parking Garage. 
  • Drilling equipment to demobilize the week of December 19th. 
Construction Update 12.16.2022 Cover Image

Construction Update 12.16.2022

Equipment to mobilize for trenching the week of December 19th

  • Equipment and personnel to mobilize on site for crane footing construction the week of December 12th. 
  • Equipment to enter and exit the site for drilling auger cast piles the week of December 12th. 
Construction Update 12.12.2022 Cover Image

Construction Update 12.12.2022

Equipment and personnel to mobilize on site for crane footing construction the week of December 12th.

  • Augercast drilling to continue the week of 12/5. 
  • Concrete & dump trucks to enter and exit the job site on S Charles St the week of 12/5. 
Construction Update 12.5.2022 Cover Image

Construction Update 12.5.2022

Augercast drilling to continue the week of 12/5.

  • Drilling equipment to mobilize on site Friday, November 18th through the week of November 21st. 
  • Drilling to begin the week of November 28th. 
Construction Update 11.21.2022 Cover Image

Construction Update 11.21.2022

Drilling equipment to mobilize on site Friday, November 18th through the week of November 21st.

  • Trenching to begin the week of November 1st. 
  • Drilling equipment to mobilize onsite Thursday November 3rd, or Friday November 4th. 
Construction Update 10.28.2022 Cover Image

Construction Update 10.28.2022

Trenching onsite the week of November 1st. Click the link below to see the full update.

  • Seattle City Light to set power pole in alley on Monday, October 24th. Expect alley closure with continued access to 999 Hiawatha parking garage. 
  • Drilling equipment to mobilize onsite Thursday, October 27th. 
Construction Update 10.21.2022 Cover Image

Construction Update 10.21.2022

Seattle City Light to set power pole in alley on Monday, October 24th. Click the link below to see the full update.

  • Seattle City Light to set power poles in the alley on Monday, October 17th. Expect alley closure with continued access to 999 Hiawatha parking garage.
  • Drilling equipment to mobilize onsite Thursday, October 20th.
Construction Update 10.14.22 Cover Image

Construction Update 10.14.22

Seattle City Light to set power poles in the alley on Monday, October 17th. Click the link below to see the full update.

  • Trucks delivering backfill will enter the site the week of October 10th. 
  • Seattle City Light will set temporary power poles the week of October 10th. Expect alley closure with continued access to 999 Hiawatha parking garage from Bush Pl. 
  • Drilling equipment will mobilize onsite the week of October 17th. 
Construction Update 10.7.22 Cover Image

Construction Update 10.7.22

Trucks delivering backfill will enter the site the week of October 10th. Click link below to see the full update.

  • Trucks will be delivering backfill into the site from S Charles St the week of October 3rd.  
  • Seattle City Light will set temporary poles the week of October 3rd . Expect alley closure with continued access to 999 Hiawatha parking garage from Bush Pl. 
  • Drilling equipment to mobilize onsite the week of October 10th. 


Construction Update 9.30.22 Cover Image

Construction Update 9.30.22

Trucks will be delivering backfill into the site from S Charles St the week of October 3rd. Click link below to see the full update.

  • Dewatering equipment delivered to site week of September 26th.
  • Pot holing in alley begins Thursday, September 29th. Expect alley closure with continued access to 999 Hiawatha parking garage from Bush Pl.
  • Temporary power poles to be installed week of October 3rd. Expect alley closure with continued access to 999 Hiawatha parking garage from Bush Pl.
  • Lane and Sidewalk closure begins October 3rd.
Construction Update 9.23.22 Cover Image

Construction Update 9.23.22

Dewatering equipment delivered to site week of September 26th. Click link below to see the full update.

  • Concrete crusher arriving Monday, September 19th. 
  • Site cleanup in preparation for drilling and support equipment. 
  • Equipment arrives September 26th. 
  • Shoring along alley begins week of September 26th. 
Construction Update 9.16.22 Cover Image

Construction Update 9.16.22

Concrete crusher arriving Monday, September 19th. Site cleanup in preparation for drilling and support equipment. Click link below to see the full update.

  • Demo of the upper level of the parking structure and sky bridge 
  • Demo of parking structure slab and footings will commence Monday and run through next week
  • Grubbing, removal of vegetation, and installation of temporary ramp from Charles into the pit will start Monday
  • During the week of 9/19, a concrete grinder will be brought onsite
  • Seattle City Light will install two temporary power poles and will offset the power line in the alley in the next two weeks.
Construction Update 9.9.22 Cover Image

Construction Update 9.9.22

Demo of the upper level of the parking structure and sky bridge. Demo of parking structure slab and footings will commence Monday and run through next week. Click link below to see the full update.

  • Equipment to mobilize on-site Thursday, September 1 and Friday, September 2
  • Parking instruction demolition resumes Tuesday, September 6
Construction Update 8.31.22 Cover Image

Construction Update 8.31.22

Equipment to mobilize on-site Thursday, September 1 and Friday, September 2. Parking instruction demolition resumes Tuesday, September 6.

Parking structure demolition will be delayed until 9/6 and the construction fence will be completed by the end of next week.

Construction Update 8.24.22 Cover Image

Construction Update 8.24.22

Parking structure demolition will be delayed until 9/6 and the construction fence will be completed by the end of next week.

  • 8/20 Crews to remove trees on Rainier Ave S - expect lane & sidewalk closure
  • 8/22 Demolition team arrives on site to remove existing parking structure - construction fence will be installed.
Construction Update 8.18.22 Cover Image

Construction Update 8.18.22

8/20: Crews to remove trees on Rainier Ave S - expect lane & sidewalk closure. 8/22: Demolition team arrives on site to remove existing parking structure - construction fence will be installed.